≤1200mm
Capacity 500t/h
Discharge size: 0-5mm mechanism sand
Raw material: Pebble
1. Project Introduction
This is a 300,000-ton river pebble crushing and sand-making project invested by Indonesia, an expected construction period of 4 months. Considering the large demand for sand and stone in the local market, it was decided to invest in creating a high-quality sand and gravel production line, which will be used for the construction of roads and real estate after completion to meet the local demand for sand and stone.
2. Equipment configuration of the production line
Material: pebble
Capacity: 500 tons/hour
Finished product: 0-5mm high-quality machine-made sand, 5-10, 10-20mm, 20-40mm aggregate
Processing technology: Wet method
Product application: Used to supplement the local sand stone gap
Main equipment: ZSW feeder, SC125 jaw crusher, SH660 single-cylinder hydraulic cone crusher, SH440 singlecylinder hydraulic cone crusher, 6X sand making machine, S5X vibrating screen (three units), XSD wheel bucket sand making machine, BX fine sand machine

a. Advanced technology and reliable equipment
The main equipment adopts advanced hydraulic regulation technology, mature process and stable and reliable performance, which makes the overall production technology, process equipment and other aspects are in the advanced level home and abroad, ensuring the efficient and stable operation of the whole project. The project adopts two-stage crushing sand making process, and the production line layout is centralized and compact which not only saves the land area, but also facilitates the inspection and maintenance of equipment.
b. Design scheme adapted to local conditions, reasonable scheme
The customer has the problem of the customer's site from a piece of barren grassland to the one about to be put into operation. Making full use of the high and low difference of site, the production line was designed reasonably and the scheme was fully optimized. Not only the amount of equipment used was saved, but also the operation cost of the customer was greatly reduced
c. Green and environmental protection
The project adopts the environmental protection process of wet production, which effectively reduces the pollution to the environment and meets the national high standard environmental requirements, achieving a dual combination of economic benefits and environmental benefits.

The crusher should be leveled during installation to make its main shaft perpendicular to the horizontal plane
Reply
The ore must be fed in the middle of the feeder, and it is not allowed to put the ore directly into the crushing chamber. Because this can easily the crusher to overload and cause uneven wear of the liner.